PAULDING — In 2020,Paulding Putnam Electric Cooperative is planning $5,673,951 in investments focused on system improvements that will directly increase the co-op’s service reliability and maintain existing facilities — all without an electric rate increase for residential or commercial members.

Primary components of the 2020 work plan include:

  • Rebuild of the Cecil Substation for improved reliability, system durability, and increased load capacity for future growth. 
  • A budgeted 28 miles of line rebuilds across Ohio and Indiana, as well as sectionalizing to reduce outage minutes.
  • Testing 3,565 poles in Adams, Jackson, and Maumee townships in Indiana and Carryall and Harrison townships in Ohio. Any poles that fail the test will be replaced. 
  • Right-of-way maintenance and tree trimming in Indiana’s Allen County and in parts of Ohio’s Paulding and Van Wert counties. 
  • Purchasing new equipment, like a bucket truck, poles, wire, etc. 

“The PPEC trustees and employees work hard to deliver electric power that is reliable, safe and cost-competitive with our neighboring utilities,” said PPEC President and CEO George Carter. “Be assured that we are working to replace aging facilities, increase efficiency and improve our service reliability – all without raising rates and also returning $1.8 million in capital credits last year to members.”

For updates throughout the year, follow PPEC on FacebookTwitterInstagram, or YouTube

Have questions about upcoming construction in your area? Give PPEC’s office a call at 800.686.2357.